- Manufacture and installation of 390 precast panels up to 20 tonnes each
- Dual-crane rotation of panels into position
- Strip and pad footings and raft slabs
- Heavy-duty aircraft hangar slabs
- Post-tensioned suspended slabs to the first level
- Bondek plant room slabs

Case Study
RAAF Base East Sale AIR5428 Pilot Training Facilities
At a glance
THE DETAILS
Client
Laing O'Rourke (head contractor)
Location
East Sale, Victoria
GBG Division
Civil Construction
Sector
Defence
Delivery Period
2017 to 2018
What we delivered
SCOPE OF WORKS
The story
HOW IT CAME TOGETHER
GBG delivered the precast and in-situ concrete package for the AIR5428 Pilot Training System facilities at RAAF Base East Sale, working for Laing O'Rourke across 2017 and 2018.
GBG manufactured and installed 390 precast panels weighing up to 20 tonnes each. The panels were dual-rotated into position using two cranes.
In-situ works included strip and pad footings, raft slabs, heavy-duty aircraft hangar slabs, post-tensioned suspended slabs to the first level and Bondek plant room slabs.