- Piling works
- Strip and pad footings and raft slabs
- Concrete stairs
- Supply and erection of precast panels, including the multi-level tower core
- Wet joints between precast elements
- Bondek suspended slabs

Case Study
RAAF Base East Sale Redevelopment
At a glance
THE DETAILS
Client
Thiess (head contractor)
Location
East Sale, Victoria
GBG Division
Civil Construction
Sector
Defence
Delivery Period
Completed 2014
What we delivered
SCOPE OF WORKS
The story
HOW IT CAME TOGETHER
GBG delivered the civil, in-situ concrete and precast works for the RAAF Base East Sale Redevelopment as subcontractor to Thiess, completing the package in 2014. The works covered a new air traffic control tower, an air traffic training facility and a physical fitness centre.
The centrepiece was the multi-level precast core of the control tower, manufactured by GBG and erected on site with wet joints between the panels. In-situ works included piling, strip and pad footings, raft slabs, concrete stairs and Bondek suspended slabs.
The package was valued at approximately $3 million and ran across two work fronts, with around 30 GBG employees on site.