Wooreen Battery Energy Storage System
Case Study

Wooreen Battery Energy Storage System

Location
Hazelwood North, Victoria
Division
Civil Construction
At a glance

THE DETAILS

Client
Zenviron (head contractor)
Location
Hazelwood North, Victoria
GBG Division
Civil Construction
Sector
Energy and renewables
Delivery Period
November 2025 to June 2026
What we delivered

SCOPE OF WORKS

  • Detailed excavation and reinforced concrete foundations for electrical and battery infrastructure
  • Transformer foundations, bunds and a reinforced concrete fire wall
  • Service culvert beneath the control room
  • Quantum battery foundations and auxiliary slabs
  • Formwork, reinforcement, placement and finishing, including cast-in connections and holding-down bolts
  • Civil and concrete coordination alongside other contractors
The story

HOW IT CAME TOGETHER

GBG was engaged by head contractor Zenviron to deliver the civil and concrete works package for EnergyAustralia's Wooreen Battery Energy Storage System in Victoria's Latrobe Valley. The works, valued at approximately $5 million, ran from November 2025 to June 2026.

The first stage covered transformer foundations, concrete bunds and a reinforced concrete fire wall approximately 13.3 metres long, 7.5 metres high and 350 millimetres thick, along with a service culvert beneath the control room. The second stage delivered the Quantum battery foundations and auxiliary slabs that support the battery storage and electrical equipment, using 32 MPa concrete for the in-situ foundations.

Across seven months GBG coordinated its works with multiple contractors on an operating construction site and resolved design issues as they arose, delivering the contracted scope within the project program and budget.

Watch

SEE IT IN MOTION

▶
Project video coming soon
Watch with sound
GBG construction team working on a large concrete project

LET'S DISCUSS YOUR PROJECT

Talk to GBG about the concrete, construction and project support your next job needs.

Talk to Our Team