Project Scope: Construction of replacement factory section, incorporating precast concrete curing chambers, and office facilities at the Boral Roofing Factory in Dingley (VIC). Works included complete project management and construction of the 1200m sq. factory to replace the existing structure. Works were completed as part of a major plant shutdown.
Contract Sum: $ 1.8 million
Client / Superintendent: Boral Roofing
Contract Type: Project Management and Construction
Completion Date: August 2007